Tag Archives: cadworx

CADWorx Command of the Month Apply Trimmed Elbow Rule

In CADWorx Plant if design need the Custom or nonstandard Angle elbow, there is an option in Piping rule to Enable the Trimmed Elbow while routing.

Go to CADWorx Plant Setup > Piping Rules > Select pulldown menu in “
Apply Trimmed Elbow Rule



By Default, the value would be “No”



Available options: No or Automatic

Places trimmed buttweld elbows in the drawing when using ROUTE.

No: Does not allow for trimmed buttweld elbows.

Automatic: Router allows for trimmed buttweld elbows.



Comments Off on CADWorx Command of the Month Apply Trimmed Elbow Rule

Filed under CADWorx, CADWorx Plant Pro, Home

CADWORX PLANT 2017 R1 SERVICE PACK 1 IS AVAILABLE

Service Pack Release Announcement

Hexagon PPM support has posted CADWorxPlant_2017_R1_SP1.zip for CADWorx Plant Version 2017 R1. This Service Pack is now available for download from Hexagon PPM’s Customer Response System. Further information about what is contained in this Service Pack is available in the Readme File link shown in the download description on the Service Packs and Fixes page.

To access this Service Pack, please follow the steps below:

  1. Logon to Hexagon PPM’s Customer Response System at https://smartsupport.intergraph.com.
  2. Select the View Downloads tab.
  3. Select CADWorx Plant.
  4. Select Service Packs and Fixes.
  5. Select the download icon or the file link of the Service Pack.

If you have trouble accessing this Service Pack or need further information, please file a Service Request for CADWorx Plant 2017 R1, and an analyst will be happy to assist you.

Continue reading

Comments Off on CADWORX PLANT 2017 R1 SERVICE PACK 1 IS AVAILABLE

Filed under CADWorx, CADWorx Plant Pro, Home

Six Times Faster Brownfield Project Execution with Intergraph® CADWorx® Solutions


Croatian engineering and analysis specialist Numikon improves productivity 640% with Intergraph CADWorx solutions
“When we first started using the Leica total station and Intergraph software the two companies trained our staff. It took them about ten days to get up to speed and start on their first project. We were particularly impressed by the in-depth knowledge of the Intergraph and Leica people. On the whole we estimate that our productivity has gone up by as much as 640% (six times)! This productivity gain means that we can minimize the on-site project time and maximize efficiency, offering our customers a very attractive package.” Mario Anić, Sales Manager from Numikon stated.
Numikon is a Croatian engineering company specializing in the calculation and analysis of mechanical, power and process equipment and components, project engineering of process and power plants, pipe stress analysis, pressure vessel design, as well as laser scanning and laser surveying.
Numikon executed a refinery project for INA-Industrija nafte d.d., a leading oil exploration, production, refining and marketing company in Croatia. INA was looking for an efficient solution to create as-built information for their Sisak refinery, and hired a consortium of companies for the project. Numikon was chosen to execute a laser scanning survey and create as-built models of the existing refinery.
The main challenge for Numikon was that the laser survey had to be undertaken while the refinery was operating, and some of the piping was difficult to access because of its location above ground, or because it was insulated, as well as the tight deadline of the project.
With the help of CADWorx fieldPipe Professional and CADWorx Plant Professional, Numikon surveyed their part of Sisak refinery in only 49 days. Using the laser surveyed data the company created all deliverables required by INA, including:
• 3D models
• Piping isometrics
• Details of piping components (valves, pressure regulators, flanges, supports, etc.)
• Tag and nameplate details
• Details of the equipment and connected piping
• Pipe stress analysis results (including required test pressure) and pipe data (wall thickness, material properties, etc.)
Curious to learn more about how Numikon improved productivity with 640%? View the whole case study (including pictures), or read the interview with Mario Anic, Sales Manager at Numikon.

Comments Off on Six Times Faster Brownfield Project Execution with Intergraph® CADWorx® Solutions

Filed under CADWorx Plant Pro, Home, News

How to add a custom actuator into CADWorx Specification editor

Comments Off on How to add a custom actuator into CADWorx Specification editor

Filed under CADWorx Plant Pro, Home

CADWorx Plant Command of the week [Total Center of Gravity]

Total Center of Gravity Generator

CADWorx Plant I tab: Pipe BOM / DB > C.G. Generator

Plant menu: Accessory > C.G. Generator

Command line: TCG

Calculates center of gravity for all components drawn in X, Y planes (2D plans) or in X, Y, Z planes (3D Model). You can use a generic attach (from Plant > Toolbars > Misc) which provides the center of gravity location and weight. For more information on specifying a center of gravity location for a generic attach, see Generic Attach or Steel – Generic Attachment.

Selection can be done by crossing, window, or selecting individual component.

Total Center of Gravity Calculation Dialog Box

Calculates the total center of gravity for all components.

Selected Components

Select – Enables you to select items to calculate the total center of gravity for that item.

Piping – Enables piping to be calculated for the total center of gravity. Reports the selected component counters in the corresponding box.

Piping Insulation – Enables piping insulation to be calculated for the total center of gravity. Reports the selected component counters in the corresponding box.

Steel – Enables steel to be calculated for the total center of gravity. Reports the selected component counters in the corresponding box.

HVAC – Enables HVAC to be calculated for the total center of gravity. Reports the selected component counters in the corresponding box.

Equipment – Enables equipment to be calculated for the total center of gravity. Reports the selected component counters in the corresponding box.

You must have a material set for the equipment, and then run EQUIPCG before you can get a center of gravity calculation for equipment in CADWorx Plant.

Report Options

Title – Specifies a title for the report that prints when CG is calculated.

Path – Specifies the location of the report file. Click the Path ellipsis to change the location and save the file.

Print report to command line – Prints the total center of gravity report to the command line.

View Report – Indicates that the software opens the report after the center of gravity calculates.

Insert drawing marker – Inserts a drawing marker for the total center of gravity.

  • Click C.G. Generator on the Pipe BOM / DB panel in the CADWorx Plant I tab. alternatively, type TCG on the command line and then press ENTER.
    • The Total CG Calculation dialog box displays.
  • Select the type of components to calculate center of gravity.
  • Enter a title for the report in the Title box.
  • Select whether you want the report to print on the command line, view the report, or whether you want to insert a marker.
  • Click Select.
    • Before you can get a center of gravity calculation for equipment in CADWorx Plant, you must have a material set for the equipment, and then you must run EQUIPCG.
    • When selecting equipment to calculate the center of gravity, you have the following choices:
      • Select all.
  • Zoom to the small white cross and select it.
  • Select the components, and then press ENTER.
    • The center of gravity calculates and the Total CG Calculation dialog box redisplays with the selected component counters in the corresponding boxes.
  • Click OK.

A center of gravity reference point and a report display.

Sample report

Comments Off on CADWorx Plant Command of the week [Total Center of Gravity]

Filed under CADWorx Plant Pro, Home

ImageGrafix Wednesday Webinar – What is New in PV Elite 2015 (27-05-2015)

We hope you enjoyed our webinar. For your reference we have attached the link for the recording. Please feel free send us your feed back : support@igfzco.com

Watch Recording

Comments Off on ImageGrafix Wednesday Webinar – What is New in PV Elite 2015 (27-05-2015)

Filed under Webinars